ABC company gives you the following standard & actual data: Raw material Standard Actual : : : Quantity Price per kg Quantity Price per kg A 80 Kgs Rs. 10 70 Kgs Rs. 11 B 20 Kgs Rs. 20 30 Kgs Rs. 18…
2ABC company gives you the following standard & actual data:
| Raw material | Standard | Actual |
|---|---|---|
| Quantity | Price per kg | |
| A | 80 Kgs | Rs. 10 |
| B | 20 Kgs | Rs. 20 |
| Required: Material cost variance |
Answer
Material Cost Variance Analysis
Standard Cost (SC):
- Material A:
- Material B:
- Total SC = Rs. 1,200
Actual Cost (AC):
- Material A:
- Material B:
- Total AC = Rs. 1,310
Material Cost Variance (MCV):
Breakdown of Variances
Material Price Variance (MPV):
- Material A:
- Material B:
- Total MPV = Rs. 10 (Adverse)
Material Usage Variance (MUV):
- Material A:
- Material B:
- Total MUV = Rs. 100 (Adverse)
Verification:
Discussion
Loading…
More Advanced Cost and Management Accounting questions
What are the features of cost accounting?TU Board 20812Mention any two features of variable cost.TU Board 20812What is overhead cost?TU Board 20812Define break even point.TU Board 20812Write down the meaning of avoidable cost.TU Board 20812Calculate fixed cost and variable cost per unit by using least square method. X = 150,000 Y = Rs. 2,500,000 XY = Rs. 85,000,000 X^2 = 5,500,000 N = 5TU Board 20812