What is Critical path method (CPM)? Construct the CPM network based on the given project details in the following table and identify the critical path. Show the necessary calculations during the CPM…

10

What is Critical path method (CPM)? Construct the CPM network based on the given project details in the following table and identify the critical path. Show the necessary calculations during the CPM network construction process. [10] ActivityDuration (Weeks)PrecedentsA Hardware Selection6-B System Configuration4-C Install Hardware3AD Data Migration4BE Data Office Procedures3BF Recruit staff10-G User Training3E, FH Install and Test System2C, D