The table give below give the information about the activities, their predecessors and time duration required to complete the activities of the project. ActivityABCDEFGHPredecessor ABA,DBC,E,FGTime…

10

The table give below give the information about the activities, their predecessors and time duration required to complete the activities of the project. ActivityABCDEFGHPredecessor--ABA,DBC,E,FGTime in weeks51263261422 Draw the network diagram and identify the critical activities and critical path. Also find the minimum time duration required to complete the project.