Draw precedence network diagram for the following activities and find the critical path. Indicate the process for shortening the project duration Activity Duration (Week) Precedence A 1 – B 2 A C 5…

10

Draw precedence network diagram for the following activities and find the critical path. Indicate the process for shortening the project duration

Activity
Duration (Week)
Precedence
A
1
–
B
2
A
C
5
A
D
2
–
E
4
C,D
F
3
–
G
4
B,E,F