CSC415 Software Project Management

Software Project ManagementTU Board 2080

Perform Earned Value Analysi of the given project. Activity Dyration(days) Precedence Cost/day (Rs.) A 6 100 B 6 A 100 C 8 B 200 D 4 B 300 The progress after the end of 16th day is as follows:…

10

Perform Earned Value Analysi of the given project.

Activity
Dyration(days)
Precedence
Cost/day (Rs.)
A
6
100
B
6
A
100
C
8
B
200
D
4
B
300

The progress after the end of 16th day is as follows:

Activity
% completation
Incurred Cost
A
100
800
B
100
400
C
25
500
D
50
400

Calculate SV, SPI. CV and CPI respectively.