CSC415 Software Project Management

Software Project ManagementTU Board 2078

Perform earned value analysis of the following project Activity Duration(days) Precedence Cost/day(RS.) A 8 200 B 4 200 C 4 A,B 300 D 4 B 400 The progress after the end of 12th day is as follows:…

10

Perform earned value analysis of the following project

Activity
Duration(days)
Precedence
Cost/day(RS.)
A
8
200
B
4
200
C
4
A,B
300
D
4
B
400

The progress after the end of 12th day is as follows:

Activity %Completion Incurred Cost
A 100 1400
B 100 400
C 75 1000
D 50 1000

Calculate SV, SPI, CV, and CPI respectively.