Software Project ManagementTU Board 2079
Perform Earned value analysis of the given project. Activity Duration(days) Precedence Cost day(Rs) Total Cost A 5 200 1000 B 5 A 200 1000 C 10 A 100 1000 D 5 A, B 200 1000 The progress after the…
10Perform Earned value analysis of the given project.
Activity
Duration(days)
Precedence
Cost day(Rs)
Total Cost
A
5
_
200
1000
B
5
A
200
1000
C
10
A
100
1000
D
5
A, B
200
1000
The progress after the end of 10th day is as follows:
| Activity | %completion | Incurred Cost |
|---|---|---|
| A | 100 | 1200 |
| B | 100 | 800 |
| C | 40 | 800 |
| D | 0 | 0 |
Calculate SV, SPI, CV and CPI respectively.
A worked answer is on its wayMeanwhile, read the Software Project Management notes for this topic.
Discussion
Loading…
More Software Project Management questions
Explain different categories of software projects. Why do you think categorization of software projects is necessary?TU Board 208220Explain three visualization techniques that can be implemented to monitor and control the project.TU Board 208220Define Break Even Point and Internal Rate of Return. Calculate payback period and ROI for the following project. Year Project 0 50000 1 20000 2 5000 3 10000 4…TU Board 208220Explain different categories of resources.TU Board 208210What are the significance of using PERT chart? Explain with respect to Z values.TU Board 208210Explain different levels of testing.TU Board 208210