Perform Earned value analysis of the given project. Activity Duration(days) Precedence Cost day(Rs) Total Cost A 5 200 1000 B 5 A 200 1000 C 10 A 100 1000 D 5 A, B 200 1000 The progress after the…

10

Perform Earned value analysis of the given project.

Activity
Duration(days)
Precedence
Cost day(Rs)
Total Cost
A
5
_
200
1000
B
5
A
200
1000
C
10
A
100
1000
D
5
A, B
200
1000

The progress after the end of 10th day is as follows:

Activity %completion Incurred Cost
A 100 1200
B 100 800
C 40 800
D 0 0

Calculate SV, SPI, CV and CPI respectively.