AccountancyNEB 2075 (old course)
Standard output in a day of 8 hours is 56 units. Rate per unit is Rs. 100 and a worker worked 180 hours in a month. Required: Monthly wages of a worker [2]
2Standard output in a day of 8 hours is 56 units. Rate per unit is Rs. 100 and a worker worked 180 hours in a month. Required:
- Monthly wages of a worker [2]
Answer
Monthly wages of a worker
Calculate standard output per hour:
Calculate standard output for 180 hours:
Calculate wages for standard output:
Since the worker worked 180 hours (exactly 22.5 days at 8 hours/day), no overtime or under/over-production applies. Thus, the total wages are: