Business MathematicsNEB 2080 (old course)
a) A contractor has to the complete the work of a road in 16 days. He employed 30 persons for 12 days and completes 57 of the work. How many more persons should be employed now in order to complete…
6- a) A contractor has to the complete the work of a road in 16 days. He employed 30 persons for 12 days and completes of the work. How many more persons should be employed now in order to complete the work in time ? [3]
- b) Mohan bought 100 kg of oranges at Rs 72 per kg. If 10 kg orange are rotten and are of no use to sell, at what rate must the remaining oranges be sold so as to gain 15% on the whole outlay ? [3]
Answer
a) Road Construction Problem (Work and Men)
Step 1: Understand the Problem
- Total work duration: 16 days
- Workers initially employed: 30 persons
- Work done in 12 days: of the total work
- Goal: Find how many additional workers are needed to complete the remaining work in the remaining time (4 days).
Step 2: Calculate Total Work in Man-Days
Work is measured in man-days (number of workers × number of days).
Work done in 12 days by 30 workers: This completes of the work.
Total work (W) in man-days:
Step 3: Calculate Remaining Work
Remaining work:
Remaining time:
Step 4: Find Required Workers for Remaining Work
Let be the additional workers needed. Total workers now = .
Work equation for remaining 4 days:
Solve for :
Final Answer
6 more persons should be employed to complete the work on time.
b) Orange Selling Problem (Profit and Loss)
Step 1: Understand the Problem
- Total oranges bought: 100 kg
- Cost per kg: Rs 72
- Rotten oranges: 10 kg (unsellable)
- Goal: Find the selling price per kg of the remaining oranges to gain 15% profit on the total cost.
Step 2: Calculate Total Cost Price (CP)
Step 3: Calculate Desired Selling Price (SP) for 15% Profit
Step 4: Calculate Sellable Quantity
Step 5: Find Selling Price per kg
Final Answer
The remaining 90 kg of oranges must be sold at Rs 92 per kg to achieve a 15% profit on the total outlay.
Discussion
Loading…
More Business Mathematics questions
If A is a square matrix then A A^T is a) a diagonal matrix b) Symmetric matrix c) Skew symmetric matrix d) Scalar matrixNEB 20811Two matrices A and B can be multiplied to get AB if a) Both matrices are square of different order. b) Both matrices are rectangular of same order. c) No.of…NEB 20811If the matrix of technical coefficients is A = bmatrix 0.1 & 0.2 \\ 0.3 & 0.4 bmatrix then Leontief matrix is a) bmatrix 0.1 & 0.2 \\ 0.3 & 0.4 bmatrix b)…NEB 20811The functions f(x) is increasing on a domain D if a) f'(x) < 0 for all x in D b) f'(x) = 0 for all x in D c) f'(x) 0 for all x in D d) f'(x) doesn't exist for…NEB 20811Which one of the following differential equation has the solution xy = c ? a) ydy + xdx = 0 b) xdy + ydx = 0 c) xdy ydx = 0 d) ydy xdx = 0NEB 20811Which one of the following is the sum of the series 1 + 12 + 14 + to a) 23 b) 12 c) 1 d) 2NEB 20811