Tribhuvan University
Bachelor of Computer Application
Semester 7 · TU Board 2024
Course Title: Software Project Management (CACS407)
Full Marks: 60Pass Marks: 24Time: 3 hours
Candidates are required to answer the question in their own words as far as possible.
Group A
Group B
Attempt any SIX question.(6 × 5 = 30)
- 2.5
Write the importance and problems in software project management
Answer comingAlso asked in 2025, 2023
- 3.5
What is a network diagram? Write the process for drawing a network diagram
- 4.5
What is a software effort estimation technique? Explain with an example.
Answer comingAlso asked in 2023
- 5.5
Why choosing of best process model is important in project management? Explain
- 6.5
Write about the framework for dealing with risk in project management.
- 7.5
What is TQM? Why it is important for software quality management.
- 8.5
What is the change control process? Write the process of SCM.
Group C
Attempt any TWO questions(2 × 10 = 20)
- 9.10
What do you mean by project scheduling? Explain the different scheduling methods.
- 10.10
Describes cost-benefits analysis techniques. Also, differentiate between flow forecasting and cost benefits techniques
- 11.10
Who is the project manager? Write the quality and qualifications of project manager and also explain his roles and responsibilities.
— The End —