Tribhuvan University
Bachelor of Information Technology
Semester 7 · TU Board 2081
Course Title: Software Project Management (BIT402)
Full Marks: 60Pass Marks: 24Time: 3 hours
Candidates are required to give their answers in their own words as far as practicable.
Group A
Attempt any Two questions.(2 × 10 = 20)
- 1.10
How Net Present Value can be utilized in choosing an appropriate project to invest on? Explain with an example. Calculate ROI if an initial investment is Rs. 5 lakh and projected benefit is Rs. 10 lakhs for 5 years (2 lakhs per year).
- 2.10
Why do you think effort estimation is required? Explain any one cost estimation model.
- 3.10
Explain rapid application development. What are its advantages and disadvantages?
Group B
Attempt any Eight questions(8 × 5 = 40)
- 4.5
How cash flow forecasting is carried out? Explain.
- 5.5
Why do you think software project management is important? Explain.
- 6.5
What is resource histogram equalization? Why is it carried out?
- 7.5
How risk assessment is carried out? Explain with an example.
- 8.5
Explain with an example when time and material contract will be beneficial.
- 9.5
How do you think timeline chart play a significant role in monitoring and controlling the project?
- 10.5
How software quality can be enhanced? Explain.
- 11.5
Explain different leadership styles.
- 12.5
Write short notes on a. Product based approach b. Project planning
— The End —