Tribhuvan University
Bachelor of Science in Computer Science and Information Technology
Semester 7 · TU Board 2078
Course Title: Software Project Management (CSC415)
Full Marks: 60Pass Marks: 24Time: 3 hours
Candidates are required to give their answers in their own words as far as practicable. The figures in the margin indicate full marks.
Group A
Attempt any Two questions.(2 × 10 = 20)
- 1.10
Perform earned value analysis of the following project
Activity
Duration(days)
Precedence
Cost/day(RS.)
A
8
200
B
4
200
C
4
A,B
300
D
4
B
400The progress after the end of 12th day is as follows:
Activity
%Completion
Incurred Cost
A
100
1400
B
100
400
C
75
1000
D
50
1000Calculate SV, SPI, CV, and CPI respectively.
Answer comingAlso asked in 2080, 2079
- 2.10
Differentiate between programme management and portfolio management. Define Payback period. How can it be used as an evaluation technique? What are its advantages and disadvantages?
- 3.10
Suppose you have been assigned to develop online voting system. List four risks that might affect the success of the system. Rank the risks based on Risk exposure. Develop contingency plan for the highest ranked risk.
Group B
Attempt Any Eight Questions(8 × 5 = 40)
- 4.5
Calculate ROI for the following project
Year
Project
0
-50000
1
5,000
2
5,000
3
20,000
4
40,000
5
50,000Answer comingAlso asked in 2080
- 5.5
Differentiate between activity-based approach and hybrid-based approach for identifying activities.
- 6.5
Why software project management is a challenging activity?
- 7.5
Draw precedence network diagram for the following and identify the critical path.
Activity
Duration(Weeks)
Precedence
A
5
B
3
A
C
5
A
D
10
B, CAnswer comingAlso asked in 2081, 2080, 2079
- 8.5
Explain Maslow's hierarchy of needs.
- 9.5
Briefly explain different quality factors.
- 10.5
Explain the process of Software Configuration Management.
- 11.5
Differentiate between Gantt chart and slip chart.
- 12.5
Short Notes
Present worth
PERT diagram
— The End —