Tribhuvan University
Bachelor of Science in Computer Science and Information Technology
Semester 7 · TU Board 2080
Course Title: Software Project Management (CSC415)
Full Marks: 60Pass Marks: 24Time: 3 hours
Candidates are required to give their answers in their own words as far as practicable. The figures in the margin indicate full marks.
Group A
Attempt any TWO question.(2 × 10 = 20)
- 1.10
Perform Earned Value Analysi of the given project.
Activity
Dyration(days)
Precedence
Cost/day (Rs.)
A
6
100
B
6
A
100
C
8
B
200
D
4
B
300The progress after the end of 16th day is as follows:
Activity
% completation
Incurred Cost
A
100
800
B
100
400
C
25
500
D
50
400Calculate SV, SPI. CV and CPI respectively.
Answer comingAlso asked in 2079, 2078
- 2.10
Elaborate on the issues and questions to be considered during strategic assessment. List the categories of direct cost and benefits and provide two examples of each.
- 3.10
Explain about different categories of resources? Highlight on the process of resource histogram equalization. Why do you think it is a crucial activity?
Group B
Attempt any EIGHT question.(8 × 5 = 40)
- 4.5
Calculate discounted payback period for the following project.
Year
Project
0
– 200,000
1
100,000
2
50,000
3
50,000
4
100,000
5
50,000Answer comingAlso asked in 2078
- 5.5
What are the objectives that activity planning aims to achieve?
- 6.5
Explain SPM framework.
- 7.5
Highlight on different types of contracts.
- 8.5
Draw precedence network diagram for the following and identify the critical path.
Activity
Duration (weeks)
Precedence
A
2
B
2
C
4
A
D
2
B
E
4
B, DAnswer comingAlso asked in 2081, 2079, 2078
- 9.5
Explain capability process model.
- 10.5
How can Software Configuration Management aid in change control and version control?
- 11.5
What are the practical implications of Risk Exposure?
- 12.5
Write short notes on:
- Future worth
- Bubble chart
— The End —