CSC415 Software Project Management

Software Project Management TU Board 2079 question paper

12 questionsSit this paper (timed)

Tribhuvan University

Bachelor of Science in Computer Science and Information Technology

Semester 7 · TU Board 2079

Course Title: Software Project Management (CSC415)

Full Marks: 60Pass Marks: 24Time: 3 hours

Candidates are required to give their answers in their own words as far as practicable. The figures in the margin indicate full marks.

Group A

Attempt any two question.(2 × 10 = 20)

  1. 1.

    Perform Earned value analysis of the given project.

    Activity
    Duration(days)
    Precedence
    Cost day(Rs)
    Total Cost
    A
    5
    _
    200
    1000
    B
    5
    A
    200
    1000
    C
    10
    A
    100
    1000
    D
    5
    A, B
    200
    1000

    The progress after the end of 10th day is as follows:

    Activity
    %completion
    Incurred Cost
    A
    100
    1200
    B
    100
    800
    C
    40
    800
    D
    0
    0

    Calculate SV, SPI, CV and CPI respectively.

    10
  2. 2.

    Explain why discounted cash flow techniques provide better criteria for project selection than net profit or return on investment. Highlight on the applicability of IRR with respect to NPV. How can it be calculated manually?

    10
  3. 3.

    List techniques that are used for progress visualization and explain them. Why do you think project monitoring and control is very challenging?

    10

Group B

Attempt any eight question.(8 × 5 = 40)

  1. 4.

    Which project would you choose from following projects and why?

    Year
    Project A
    Project B
    0
    -40,000
    -80,000
    1
    5,000
    2,000
    2
    15,000
    10,000
    3
    5,000
    70,000
    4
    40,000
    50,000
    5
    50,000
    50,000

    5
  2. 5.

    What are different stages required to create a project schedule?

    5
  3. 6.

    Explain project management cycle.

    5
  4. 7.

    Draw CPM network diagram for the following and identify the critical path.

    Activity
    Duration(weeks)
    Precedence
    A
    4
    B
    4
    A
    C
    2
    A
    D
    6
    B, C

    5
  5. 8.

    Highlight on different types of leadership styles.

    5
  6. 9.

    Differentiate between verification and validation. List testing principles.

    5
  7. 10.

    What is a baseline? Why Software Configuration Management is a critical activity?

    5
  8. 11.

    Why PERT chart is an efficient technique? Explain estimated time, standard deviation and Z-value with respect to PERT chart.

    5
  9. 12.

    Short Notes:

    • a) Annual Worth

    • b) Risk Exposure

    5

— The End —