Tribhuvan University
Bachelor of Science in Computer Science and Information Technology
Semester 7 · TU Board 2081
Course Title: Software Project Management (CSC415)
Full Marks: 60Pass Marks: 24Time: 3 hours
Candidates are required to give their answers in their own words as far as practicable. The figures in the margin indicate full marks.
Group A
Attempt any TWO questions.(2 × 10 = 20)
- 1.10
Draw precedence network diagram for the following activities and find the critical path. Indicate the process for shortening the project duration
Activity
Duration (Week)
Precedence
A
1
–
B
2
A
C
5
A
D
2
–
E
4
C,D
F
3
–
G
4
B,E,FAnswer comingAlso asked in 2080, 2079, 2078
- 2.10
Why do you think economic analysis is an important activity? Explain the terms present worth, future worth and annual worth. Illustrate on uniform gradient cash flow.
- 3.10
What are testing principles? List different test strategies. Explain SQA plan.
Group B
Attempt any EIGHT questions.(8 × 5 = 40)
- 4.5
Explain different types of project plan.
- 5.5
Suppose the cost price of 1 piece of USB drive is Rs. 1000. You bought 1000 pieces and also paid Rs 2000 as a delivery charge. Calculate ROI if you would sell those USB drives for Rs. 1500 per piece.
- 6.5
Why do you think resource smoothening and resource balancing is required? Explain how it is carried out?
- 7.5
Explain any two methods of visualizing progress of a project
- 8.5
What are different stages in contract? Explain.
- 9.5
What is SEI-CMM? Explain its importance
- 10.5
Highlight on configuration management responsibilities.
- 11.5
Explain the process of risk analysis.
- 12.5
Write short notes on
a) Baseline
b) Schedule variance
— The End —