CSC415 Software Project Management
Software Project Management: most repeated questions
Questions that have come up in more than one paper, matched by what they ask rather than exact wording. Most repeated first.
- 4×Asked in 2081, 2080, 2079, 2078Draw precedence network diagram for the following activities and find the critical path. Indicate the process for shortening the project duration Activity Duration (Week) Precedence A 1 – B 2 A C 5 A D 2 – E 4 C,D F 3 – G 4 B,E,FAnswer coming10
See the wording in each paper
- Draw precedence network diagram for the following activities and find the critical path. Indicate the process for shortening the project duration Activity Duration (Week) Precedence A 1 – B 2 A C 5…TU Board 2081
- Draw precedence network diagram for the following and identify the critical path. Activity Duration (weeks) Precedence A 2 B 2 C 4 A D 2 B E 4 B, DTU Board 2080
- Draw CPM network diagram for the following and identify the critical path. Activity Duration(weeks) Precedence A 4 B 4 A C 2 A D 6 B, CTU Board 2079
- Draw precedence network diagram for the following and identify the critical path. Activity Duration(Weeks) Precedence A 5 B 3 A C 5 A D 10 B, CTU Board 2078
- 3×Asked in 2080, 2079, 2078Perform Earned Value Analysi of the given project. Activity Dyration(days) Precedence Cost/day (Rs.) A 6 100 B 6 A 100 C 8 B 200 D 4 B 300 The progress after the end of 16th day is as follows: Activity % completation Incurred Cost A 100 800 B 100 400 C 25…Answer coming10
See the wording in each paper
- Perform Earned Value Analysi of the given project. Activity Dyration(days) Precedence Cost/day (Rs.) A 6 100 B 6 A 100 C 8 B 200 D 4 B 300 The progress after the end of 16th day is as follows:…TU Board 2080
- Perform Earned value analysis of the given project. Activity Duration(days) Precedence Cost day(Rs) Total Cost A 5 200 1000 B 5 A 200 1000 C 10 A 100 1000 D 5 A, B 200 1000 The progress after the…TU Board 2079
- Perform earned value analysis of the following project Activity Duration(days) Precedence Cost/day(RS.) A 8 200 B 4 200 C 4 A,B 300 D 4 B 400 The progress after the end of 12th day is as follows:…TU Board 2078
- 2×Asked in 2080, 2078Calculate discounted payback period for the following project. Year Project 0 – 200,000 1 100,000 2 50,000 3 50,000 4 100,000 5 50,000Answer coming5